PSERN Project Schedule

The following Project schedule timeframes are subject to change, but are accurate as of the 4/22/21:

Site Construction (building radio towers and infrastructure)
April 2016 – September 2021

Programming Templates (developing/programming per radio)
October 2019 – November 2021

Radio Frequency Coverage Testing (testing end-user signal quality)
March 2021 – November 2021

Radio End User Pilot Testing (proof of concept end user testing)
December 2021 – January 2022*

Radio Deployment & Transition (distribution of agency radios)
January 2022 – November 2022*

Full System Acceptance (Transition operations to PSERN Operator)
March 2023*

* new since last month